Iowa · Midwest Wind Corridor

The American wind belt. Iowa generates over 60% of its electricity from wind, the highest share of any US state. Meta operates its largest global data center campus in Altoona. Microsoft, Google, and Apple all have major facilities. Wind PPAs here are among the cheapest in the world, and the flat terrain means excellent wind capacity factors.

wind-poweredcheapest-ppasmeta-hq
DC Capacity
900 MW
Grid Share
2%
PPA Price
$22/MWh
Grid Price
$30/MWh
Water Stress
Low
Growth Rate
+20%
Permit Wait
18 months
Cooling
Evaporative
Natural Cooling
6 months/yr
Avg Temperature
10°C

Grid composition · 70% carbon-free · 28% fossil

62%
18%
10%
Nuclear6%
Renewable62%
Hydro2%
Gas18%
Coal10%
Other2%
Carbon-free
70%
Nuclear + renewable + hydro
Fossil
28%
Gas + coal

4 operators · 830 MW tracked capacity

Capacity
350 MW
Share
42%
Capacity
200 MW
Share
24%
Capacity
180 MW
Share
22%
Capacity
100 MW
Share
12%

3 infrastructure constraints identified

  • Wind intermittency requires grid-scale batteries
  • Transmission constraints to major population centers
  • Severe weather (tornadoes, ice storms) risk

Nuclear, renewable, and geothermal deals

No major energy deals tracked in this region.

This does not mean no deals exist. BenchGecko tracks publicly announced datacenter energy deals above 100 MW.

Cooling water consumption · stress level · source

Water stress
low
Daily consumption
6 MGal
Water source
Des Moines River, groundwater
Cooling method
Evaporative

Planned and under construction capacity

Under construction
500 MW
Planned
1,200 MW
Permit wait
18 months
Growth rate
+20%
Capacity pipeline1,700 MW total pipeline
Under construction
Planned

Every data point on this page is reproducible

Compare datacenter power across all tracked regions